Purpose: Automation, remote assistance, and reduced operating costs.
Development of hardware, software, and integrations needed to monitor the status of the disconnect switches and other substation assets with data acquisition and processing using LIDAR, visual, and thermal sensors.
Monitoring the status of switch-disconnectors and other substation assets by applying artificial intelligence to data acquired by LIDAR, visual and thermal sensors
IVISION
R$ 5,5MM
Yes
Design
January/2022
Kickoff
May/2022
Prototype
August/2023
Software
December/2023
Validation
April/2024
Technology Transfer
May/2024
P.S.:
Deadline: May/2024